Grant of Licence for Construction/ Reconstruction of any structure

Any person intending to erect,reconstruct,alter or modify any structure shall make an written application to the panchayat in accordance with the following order issued by the Government in this regard.

Order

30/3/DP-99

In order to simplify the procedure for the grant of permission for the construction of building, the government is pleased to issue the following instruction for strict compliance of the panchayat or the concerned authority.

1) Every person seeking permissiom for construction of the building shall prepare four sets of building plans and drawing and submit the same to the panchayat along with all necessary documents as required by the Goa Daman & Diu Village Panchayat, {Regulation of Building} Rules, 1971.

2) The Village Panchayat Secretary or any other person authorized by Panchayat in this behalf shall acknowledge the application. The Panchayat Secretary shall scrutinize the application and place the same before the Sarpanch. Within 2 days from the date of receipt of the application. In case if the application is complete in all respects, the Sarpanch shall forward the plains and drawing to the Town Planner of the concerned taluka in duplicate and simultaneously one set of plans & drawing drawing to the Assistant Engineer of PWD/Technical officer. In case the application is incomplete. The Panchayat Secretary shall return the same to the applicant within the week with the direction to resubmit the application after complying with the observation rased by the panchayat.

3) The Town Planner and the Technical Officer shall communicate their comments/views within two weeks from the date of the receipt of the plans and drawing from the panchayat.

4) The Town Planner shall scrutinize the plans and convey his comments on the following aspects:-

a} The area of the plot

b} The area allowed to be converted by the Dy. Collector

c} The permissible FAR

d} FAR proposed for construction

e} Height of the building.

f} Number of units allowed and their purpose.

g} Total built up area.

h} The area kept for car parking, open space etc.

i} Set back approved North, South, East, & West.

j} Area of the existing structure incase of reconstruction.

k} Access to the proposed construction

l} Whether any traditional access or footpath are existing

m} The zone in which the proposed construction falls and any other information which may be relevant.

 

 

a) Requirement are as follows:

 

Sr. No

Documents

Number of Copies

1

Application for Construction License in prescribed format (As per Appendix? A3)

1

2

Questionnaire duly authenticated by PDA/TCPD (Original)(As per Appendix ? B1)

1

3

 Technical Clearance Order from town planner., town and country Planning Department Alongwith approved Detailed plans, Elevations and Section, Structural Design, Site Plan, Location Plan, parking layout plan, Contour Plan in case of sloping sites

3

4

Valuation certificate from concern Architect/Engineer (Govt. Approved)

1

5

Structural Liability Certificate from Concern Engineer

1

6

Certificate of Conformity of Regulation from concern Architect

1

7

Sanad from competent authority

1

8

Approval/NOC from concerned Health officer on Sanitation point of view alongwith approval of septic tank drawing

1

9

Document showing ownership of land (Attested True Copy)

 Title Documents/Sale Deed

Survey Plan (Latest True Copy)

 Copy of index of land (Form I & XIV) latest true copy

1

10

Approval from CRZ if Required

1

11

NOC from other agencies if applicable

1. Chief Inspectors of factories and Goa State Pollution Control Board: in case of industrial building

2. Chief Fire Officer: In case of high – rise buildings

3. Electricity Department : in case the electric line is passing through the property

4. Health officer:  from sanction point of view

 5. Chief controller of explosives and chief fire officer : incase of hazardous building

6. Goa Coastal Zone management Authority: in case the construction/ development falls within 500 mtrs. Of high tide line of sea and 100 mtrs of river edge

1

12

Affidavit stating that applicant has followed proper procedure and submitted required documents without any malpractice as well as affidavit regarding disposal of debris/ Garbage generated during the course of construction to be disposed off in a scientific and un hygienic manner at his own cost with in his court yard

1

 

b) Once received by the Panchayat the same is placed before the Panchayat meeting.

 

c) Site inspection conducted, if decided by the Panchayat.

 

d) If found in order and there are no differences of opinion between the V.P. Secretary, Sarpanch, and V.P. member, (i.e. the inspection team) construction license is issued, else placed for the Panchayat meeting again.

 

e) Minimum time taken to issue is within 30 days on approval after placing the file for Panchayat meeting.

 

License for Hotels/ Shops/ Restaurant/ Eating House/ Coffee House/ Sweet Meat Shop/ Bakery/ Boarding etc

License for Hotels/ Shops/ Restaurant/ Eating House/ Coffee House/ Sweet Meat Shop/ Bakery/ Boarding etc. A renewable license for hotels/shops/restaurants/ eating house/ Coffee house/ sweet meat shop/ bakery/boarding, etc. is issued by the Panchayat under section 70 of The Goa Panchayat Raj Act,1994. A person requiring such a license should apply to the Sarpanch. After carrying out necessary inquiry, the matter is placed before the Panchayat body which through its resolution decides on the issue of such permission. The Secretary shall thereafter implement the resolution of the Panchayat.

Permission for Repairs of House/Structure [Maximum Time Limit for Providing Services One Month]

i) A panchayat may grant permission for the repairs of a house/structure without the approval of Town & Country Planning Department within the existing plinth area. However the Panchayat should satisfy itself that the applicant is the owner of the house and has furnished all the other required documents before grant of such permission.

ii) In order to keep an effective control and avoid any misuse of such repairs license granted by the Panchayat, formats for granting such a license, Inspection Report and the Application form for issue of repairs permission have been prescribed by this Department vide Circular No.15/77/DP/CIR/200/6983 dated 6.9.2002. (See Annexure- 5)

iii) The Panchayat shall ensure that the repairs permission is issued only to the existing houses which were constructed after obtaining valid licenses or the house is recorded in the House Tax Register for the last more than five years.

iv) The Panchayat shall compulsorily obtain and retain in the file of the concerned party, the details of repairs, the Inspection Report and the copy of the permission granted in the prescribed formats.

 

a) Requirements are as follows:

  • Application in the prescribed proforma.
  • Ownership Documents / Rough Sketch.
  • House Tax Receipt
  • Placed for the Panchayat meeting and forwarded to B.D.O.

b) Placed for the Panchayat meeting once approval is received from B.D.O. Site inspection is conducted, if decided by the Panchayat.

 

c) If found in order and there are no differences of opinion between the V.P. Secretary, Sarpanch, and V.P. member, (i.e. the inspection team) permission is issued Else placed for the Panchayat meeting again.

 d) Permission issued within 30 days from the date of approval of meeting.

Permission for construction of factories/ Installation of Machinery [Maximum Time Limit for Providing Services One Month]

Permission for construction of factories/ Installation of Machinery. A renewable permission for construction or establishment of any factory, workshop or workplace or for installation of machinery or manufacturing plant is issued by the Panchayat under section 68 of The Goa Panchayat Raj Act, 1994. A person requiring such permission should apply to the Sarpanch. After carrying out necessary inquiry, and after verifying all the relevant documents, the matter is placed before the Panchayat Body which through its resolution decides on the issue of such permission. The Secretary shall thereafter implement the resolution of the Panchayat.

 

Requirements are as follows:

  • Application from the applicant to with details of place where the construction of factories/ Installation of Machinery.
  • House Tax receipt / Ownership Document or NOC from the owner.
  • Swearing on Stamp Paper for safe disposal of Garbage
  • NOC from fire dept.
  • NOC from Health Dept.
  • Any other NOC’s as the case may be
License for using any place for Trade, Business or Industry [Maximum Time Limit for Providing Services One Month]

License for using any place for Trade, Business or Industry. A renewable license for construction or establishment of any factory, workshop or workplace or for installation of machinery or manufacturing plant is issued by the Panchayat under section 69 of The Goa Panchayat Raj Act, 1994. A person requiring such a License should apply to the Sarpanch. After carrying out necessary inquiry, and after verifying all the relevant documents, the matter is placed before the Panchayat Body which through its resolution decides on the issue of such license The Secretary shall thereafter implement the resolution of the Panchayat.

 

Requirements are as follows:

  • Application from the applicant to with details of place where the Trade / Business or Industry is to be established.
  • House Tax receipt / Ownership Document or NOC from the owner.
  • Swearing on Stamp Paper for safe disposal of Garbage
  • NOC from fire dept.
  • NOC from Health Dept.
  • NOC from Food and Drugs Dept.
  • Any other NOC’s as the case may be
Licensing for Shops

A renewable license is issued by the Panchayat for permanent and temporary shops under section 71 of The Goa Panchayat Raj Act, 1994. Any person requiring such a license should apply to the Sarpanch. After carrying out necessary inquiry, and after verifying all the ownership documents, the matter is placed before the Panchayat body which through its resolution decides on the issue of such permission. The Secretary shall thereafter implement the resolution of the Panchayat.

Income Certificate [Maximum Time Limit for Providing Services One Week]

A person desiring to get an Income Certificate should apply to Sarpanch/Secretary along with an affidavit sworn before a Magistrate/Notary, xerox copy of Ration Card and other relevant income documents. After verifying the documents and conducting a local inquiry in to the facts and merits of the case, the Village Panchayat Secretary shall issue the Income Certificate, duly attested by the Sarpanch and countersigned by the concerned Block Development Officer.

Requirements are as follows:-

  • Application from the applicant
  • Self Declaration with photo affixed of the applicant
  • ID proof (House Tax Receipt / Ration Card / Epic Card / Adhar Card)
  • Any other document concerning the purpose of the certificate
Birth / Death Certificate [maximum Time Limit For providing Services One Day]

The Village Panchayat Secretary also functions as Registrar of Births and Deaths under the Registration of Births and Deaths Act, 1969. The first Birth or Death registration certificates are issued by the Secretary immediately after the registration has taken place. An abstract of Births and Deaths Registrars is also available at the office of the V.P. Secretary which may be obtained from him on payment of prescribed fees.

 

a) Requirements are as follows:-

 

  • Application from the applicant with details of Birth / Death

 

b) Minimum time taken to issue is 01 day.

Occupancy Certificate [Maximum Time Limit for Providing Services One Month]

As soon as the building is ready for occupation, the licensee should obtain first, the certificate from the Project Engineer that the building is complete in all respects in accordance with the approved plans and that the said building is ready for occupation. The licensee, thereafter, shall approach the Panchayat for grant of occupancy certificate which will be referred by the village panchayat to the Technical Officer for his opinion. A copy of the file shall also be forwarded to the Town and Country Planning Department for their approval. Once the Technical Officer and the Town Planner grants clearance for issue of occupancy certificate, the case shall be referred to the Block Development Officer for payment of the infrastructure tax if the built up area exceeds 100 sq. mts. The rate of tax is presently charged @ Rs. 40/- per sq. m. on the floor area as per the rates notified under the provisions of Goa Tax on Infrastructure Act, 1997. After payment of the infrastructure tax, the Panchayat Secretary shall issue the Occupancy Certificate pursuant to the resolution of the Panchayat.

Exemptions: Buildings constructed for educational institutions, industrial enterprises or by any other non-profitable organizations as may be notified by the Government in public interest are exempted from payment of Infrastructure Tax.

Residence Certificate [ONE WEEK]

a) Requirements are as follows:-

 

  • Application from the applicant mentioning the details as required to be filled in on FORM III stating the purpose for which it is required and where to be produced.
  • Birth Certificate
  • ID proof (Ration Card / Epic Card/Adhaar Card)

 

b) Minimum time taken to issue is within 7 days after verification of the application in the Panchayat records.

Character Certificate [ONE WEEK]

a) Requirements are as follows:-

 

  • Application from the applicant mentioning the details of the purpose for which it is required and where to be produced.
  • Birth Certificate
  • ID proof (Ration Card / Epic Card/Adhaar Card)

b) Minimum time taken to issue is within 7 days after verification of the application and enclosures.

Dependency Certificate [ ONE WEEK]

a) Requirements are as follows:-

 

  • Application from the applicant mentioning the name of the dependant and the department where the Certificate is to be produced
  • Ward Member signature on the application
  • ID proof (Adhaar card / Epic Card/Ration Card)

 

b) Minimum time taken to issue is within 7 days after verification of the application and enclosures.

Poverty Certificate [ONE WEEK]

a) Requirements are as follows:-

 

  • Application from the applicant mentioning the department where the Certificate is to be produced
  • ID proof (Adhaar Card / Epic Card)

 

b) Minimum time taken to issue is within 7 days after verification of the application and enclosures.

Divergency Certificate [ONE WEEK]

a) Requirements are as follows:-

 

  • Application from the applicant mentioning the purpose of the certificate and department where the Certificate is to be produced
  • ID proof (Adhaar Card / Epic Card)
  • Documents pertaining to the divergence of names sought.

 

b) Minimum time taken to issue is within 7 days after verification of the application and enclosures.

Bonafide Fisherman Certificate [ ONE WEEK]

a) Requirements are as follows:-

 

  • Application from the applicant mentioning the purpose of the certificate and department where the Certificate is to be produced
  • ID proof (Adhaar Card / Epic Card)
  • Documents pertaining to the divergence of names sought.

 

b) Minimum time taken to issue is within 7 days after verification of the application and enclosures.

Occupation Certificate [ONE WEEK]

a) Requirements are as follows:-

 

  • Application from the applicant mentioning the purpose of the certificate and department where the Certificate is to be produced
  • ID proof (Adhaar Card / Epic Card)
  • Documents pertaining to the divergence of names sought.

 

b) Minimum time taken to issue is within 7 days after verification of the application and enclosures.

NOC for water Connection [20 DAYS]

a) Requirements are as follows:-

 

  • Application mentioning the H. No., name of the Owner and purpose
  • Copy of House Tax Receipt
  • NOC from the Owner if the Ownership if House Tax Records differs.

b) Placed for the Panchayat meeting

 

c) Site inspection conducted, if decided by the Panchayat.

 

d) If found in order and there are no differences of opinion between the V.P. Secretary, Sarpanch, and V.P. member, (i.e. the inspection team) NOC for Water           

        Connection is issued, else placed for the Panchayat meeting again.

 

  1. e) Minimum time taken to issue is within 20 days on approval after placing it for the Panchayat body meeting.
NOC For electricity Connection [20 Days]

a) Requirements are as follows:-

 

  • Application mentioning the H. No., name of the Owner and purpose
  • Copy of House Tax Receipt
  • NOC from the Owner if the Ownership if House Tax Records differs.

 

b) Placed for the Panchayat meeting

 

c) Site inspection conducted, if decided by the Panchayat.

 

d) If found in order and there are no differences of opinion between the V.P. Secretary, Sarpanch, and V.P. member, (i.e. the inspection team) NOC for

       Electricity Connection is issued, else placed for the Panchayat meeting again.

 

e) Minimum time taken to issue is within 20 days on approval after placing it for the Panchayat body meeting.

NOC for Road Cutting [20 Days]

a) Requirements are as follows:-

 

  • Application from the applicant to cut the road with exact address
  • Purpose for which the road cutting is required and place where the NOC is to be submitted
  • NOC from the Owner if necessary.
  •  

 

b) Placed for the Panchayat meeting

 

c) Site inspection conducted, if decided by the Panchayat.

 

d) If found in order and there are no differences of opinion between the V.P. Secretary, Sarpanch, and V.P. member, (i.e. the inspection team) NOC for Road

       Cutting is issued, else placed for the Panchayat meeting again.

 

   e) Minimum time taken to issue is within 4 days on approval after placing it for the Panchayat body meeting

NOC For Running General Stores/Bar/Liquor Shop/Establishment [20 Days]

a) Requirements are as follows:-

 

  • Application from the applicant to with details of place where the General Store/Bar/Liquor Shop/Establishment business is to be started.
  • House Tax receipt / Ownership Document or NOC from the owner.
  • Self Declaration Paper for safe disposal of Garbage
  • NOC from fire dept.
  • NOC from Health Dept.
  • NOC from Food and Drugs Dept.

b) Placed for the Panchayat meeting

 

c) Site inspection conducted, if decided by the Panchayat.

 

d) If found in order and there are no differences of opinion between the V.P. Secretary, Sarpanch, and V.P. member, (i.e. the inspection team) NOC for

      Running General Store is issued, else placed again for the Panchayat meeting.

 

e) Minimum time taken to issue is within 20 days on approval after placing it for the Panchayat body meeting.

Transfer of House Tax Record

a) Requirements are as follows:-

 

    • Application from the concerned.
    • Deed of Sale & Agreement of Sale
    • House Tax receipt / Ownership Document or NOC from the owner.
    • If the Owner is deceased, Copy of Death Certificate to be attached
    • Self Declaration stating the NOC from other legal heirs. Copy of Death Certificate to be attached incase any heir is deceased.

 

b) Placed for the Panchayat meeting

 

c) If found in order and there are no differences of opinion between the Panchayat than the same is transferred in the name of the applicant.

 

d) Minimum time taken to transfer after the same is approved for the Panchayat body meeting.

Correction in Birth & Death Record [ ONE MONTH ]

a) Requirements are as follows:-

 

  • Application from the applicant mentioning the corrections to be done.
  • Swearing on Stamp Paper mentioning the erroneous names and the correct names
  • Relevant Proof / certificates to support the correction

 

b) Minimum time taken is within 30 days after scrutinizing the application and enclosures.

c) This service cannot be applied online.

Issue of Certified Copy Resolution [ 15 Days ]

a) Requirements are as follows:-

 

  • Application from the applicant mentioning the Resolution number and date of the resolution taken.

 

b) Minimum time taken is within 15 days after scrutinizing the application and enclosures.

Issue of Information Under RTI Act 2005 [ ONE MONTH ]

a) Requirements are as follows:-

    • Application from the applicant mentioning the details of information sought to be furnished under RTI, 2005.
    • Court Fee of Rs. 10 on the application.

 

b) Maximum time taken is within 30 days.

Primary Bread Winner Certificate [ 10 Days ]

a) Requirements are as follows:-

 

  • Application from the applicant mentioning the department where the Certificate is to be produced
  • ID proof (Adhaar Card / Epic Card/Ration Card)
  • Income Certificate issued by competent authority

 

b) Maximum time taken is within 10 days.